Assalamu Alaikum!
 
Alhamdulillah, this week, we have made the following progress in the ICF Expansion Project:
 
  • The drywall hard top ceilings have been primed and are ready for painting! Final ceiling tiles are now being installed throughout the building.
  • All bathroom tiling has been completed (floor and walls). Additional floor installation work will be beginning soon inshaAllah.
  • Installation of the building intrusion and access control systems is in progress. 
  • Plumbing fixture installation is currently in progress. In the pictures below, you can see the toilets, sinks, water fountains, and other fixtures being installed or awaiting installation.
  • The cabinets, lockers, and shoe racks are currently being installed. In the pictures, you will see the shoe racks, office space cabinets, and other wood accents/storage fixtures!
 
As always, please remember to donate generously to support this project and help us keep the first-floor opening on track for Ramadan 2023! Please see below for some progress pictures.