Alhamdulillah, this week, we have made the following progress in the ICF Expansion Project:

  • The floor has been installed for the majority of the building, Alhamdulillah. The lobby floor installation will take place later this week and be complete next week, inshaAllah.
  • All ceiling tiles in the building have been fitted.
  • Installation of the security panels and sensors has begun, and in the coming weeks there will be additional low voltage and A/V finalization work occurring inshaAllah.
  • Continued plumbing work is underway in the restrooms, kitchen, and other areas.
  • Final paint work is underway in the restrooms and lobby areas of the building.
  • The majority of the interior doors and door hardware have now been installed. The viewing glass for the windows is currently being fitted.
  • Outdoor irrigation work is complete, and landscaping work has begun.
  • And much more!