Assalamu Alaikum!
Alhamdulillah, this week, we have made the following progress in the ICF Expansion Project:
- The floor has been installed for the majority of the building, Alhamdulillah. The lobby floor installation will take place later this week and be complete next week, inshaAllah.
- All ceiling tiles in the building have been fitted.
- Installation of the security panels and sensors has begun, and in the coming weeks there will be additional low voltage and A/V finalization work occurring inshaAllah.
- Continued plumbing work is underway in the restrooms, kitchen, and other areas.
- Final paint work is underway in the restrooms and lobby areas of the building.
- The majority of the interior doors and door hardware have now been installed. The viewing glass for the windows is currently being fitted.
- Outdoor irrigation work is complete, and landscaping work has begun.
- And much more!