Alhamdulillah, this week we have made the following progress in the ICF Expansion Project
- More exterior stone work and mortar installation
- Sidewalks poured and complete for the majority of the perimeter – the rest will be poured in the coming weeks iA
- Low voltage – cabling for the audio system in progress, wall boxes for fire alarm strobes installed
- Drywall – initial coat of paint applied in many areas, patch work and touch ups in progress
- Ceiling Tiles – grid installed in the majority of the building
- HVAC – rooftop units delivered. Ceiling duct installation has begun in the ceiling grid
- Plumbing – plumbing for wudhu faucets and other fixtures roughed in
As always, please remember to donate generously to support this project and help us keep the first floor opening on track for Ramadan 2023! Please see below for some progress pictures.