Alhamdulillah, this week, we have made the following progress in the ICF Expansion Project:
  • The drywall hard top ceilings have been primed and are ready for painting! Final ceiling tiles are now being installed throughout the building.
  • All bathroom tiling has been completed (floor and walls). Additional floor installation work will be beginning soon inshaAllah.
  • Installation of the building intrusion and access control systems is in progress. 
  • Plumbing fixture installation is currently in progress. In the pictures below, you can see the toilets, sinks, water fountains, and other fixtures being installed or awaiting installation.
  • The cabinets, lockers, and shoe racks are currently being installed. In the pictures, you will see the shoe racks, office space cabinets, and other wood accents/storage fixtures!
As always, please remember to donate generously to support this project and help us keep the first-floor opening on track for Ramadan 2023! Please see below for some progress pictures. 

 
Exterior
20240117_094059.jpg20240117_094055.jpg20240117_093621.jpg 20240117_093611.jpg
Reception & Lobby
20240117_093638.jpg20240117_094039.jpg
Multipurpose Banquet Hall
 20240117_093647.jpg
20240117_093809.jpg
 
 Classrooms & Offices
20240117_094014.jpg20240117_093922.jpg20240117_093903.jpg 20240117_093709.jpg20240117_093748.jpg
 
Restrooms & Wudu Areas
20240117_094000.jpg20240117_093721.jpg20240117_093949.jpg20240117_093842.jpg20240117_093728.jpg
 
20240117_093755.jpg20240117_093911.jpg20240117_093656.jpgHallways & Misc
 